| 1 |
State |
Andhra Pradesh |
| 2 |
Project Name |
Development of six Lane Chittoor – Thatchur Highway of NH716B from Km. 61/380 to (Veera Kaveri Raja Puram) to Km. 96/040 (Pondavakkam) on Hybrid Annuity Mode Under Bharatmala Pariyojna, in the state of Andhra Pradesh and Tamilnadu (Package -III) |
| 3 |
Project Details |
NH–716B |
| 4 |
Scheme / Phase |
Bharatmala Pariyojana |
| 5 |
Mode of the Execution |
Hybrid Annuity Mode |
| 6 |
ROW Details |
Six Lanning (ROW Width) From Km.61.380 to Km.61.460- varying From Km.61.460 to Km.61.850- 80 m From Km.61.850 to Km.94.700- 60 m From Km.94.700 to Km.96.040- 80 m |
| 7 |
Length of the Project (in Km) |
34.660 |
| 8 |
Total Project Bid Cost (in Cr) |
1041.50 |
| 9 |
Estimated Project Cost (in Cr) |
844.36 |
| 10 |
No. of Toll plazas/ Interchange Ramp Plaza |
1 (At Km.95+444) |
| 11 |
Concessionaire Name |
M/s KNR Ramagiri Infra Private Limited, Hyderabad. |
| 12 |
EPC Contractor Name |
M/s KNR Constructions Ltd |
| 13 |
Independent Engineer |
M/s Dhruv Consultancy Services Limited, Joint Venture with Global Infra Solutions Association with Kaius Consultancy Pvt Ltd |
| 14 |
Safety Consultant |
Sri Info Tech, Hyderabad. |
| 15 |
RFP Date |
25.11.2020 |
| 16 |
Bid Due Date |
07.04.2021 |
| 17 |
Bid Opening Date |
04.06.2021 |
| 18 |
Issue of Award (LOA Date) |
14.09.2021 |
| 19 |
Concession Agreement Date |
10.11.2021 |
| 20 |
Joint memorandum Date (MOU) |
31.12.2022 |
| 21 |
Appointed Date |
25.01.2023 |
| 22 |
Pavement Type |
Flexible |
| 23 |
Design Period |
20 Years Main Carriageway & Slip Road (Ramp Interchange) 15 Years Connecting Road |
| 24 |
Construction Period (in Days) |
730 Days |
| 25 |
O&M Period (in Years) |
15 Years |
| 26 |
Performance Security Amount Rs. / BG No. & Submission Date |
31.245 Cr / IBG120471 dated 01.12.2021 & Submitted on 03.12.2021(Extension on 16.05.2023 Valid from 01.06.2023 to 29.02.2024) (BG released vide PD letter No.203 dt 16.02.2024) |
| 27 |
Physical Progress Achieved as per site |
98.905% |
| 28 |
Financial Progress Achieved as per Approved Schedule-G |
98.905% |
| 29 |
Provisional Certificate |
16-12-2024 -IE issued PCC-1 vide lr no.DCSL-GIS-KCPL/IE-NHAI/CHIT-THAT/PKG-2/2025/782 dated 12.05.2025 (from Km.61+380 to Km.91+965 i.e, 30.585 Kms) IE recommended PCC-2 (from Km.91+965 to Km.96+040 i.e,4.075 Kms) w.e.f, 06.09.2025 vide lr no.DCSL-GIS-KC |