Main Carriageway progress up to 31.01.2026
|
Sl. No. |
Description |
Unit |
Total Scope |
Up to Date |
Up to Previous |
This Month |
Remarks |
|
(Length Kms) |
(Length Kms) |
(Length Kms) |
|||||
|
1 |
Site Clearance (C&G) |
Km |
34.660 |
34.660 |
34.660 |
0.000 |
|
|
2 |
Earthwork up to Subgrade Top-500mm |
Km |
32.006 |
32.006 |
32.006 |
0.000 |
|
|
3 |
GSB - 200 mm (Granular Subbase) |
Km |
32.006 |
32.006 |
32.006 |
0.000 |
|
|
4 |
CTB-170mm(Cement Treated Base) |
Km |
32.006 |
32.006 |
32.006 |
0.000 |
|
|
4 |
AIL - 100 mm (Aggregate Inter layer) |
Km |
32.006 |
32.006 |
32.006 |
0.000 |
|
|
5 |
Shoulders |
Km |
32.006 |
32.006 |
32.006 |
0.000 |
|
|
6 |
DBM- Layer – 60 mm |
Km |
32.006 |
32.006 |
32.006 |
0.000 |
|
|
8 |
BC - 40 mm (Bituminous Concrete) |
Km |
34.660 |
34.660 |
34.660 |
0.000 |
|
Connecting Roads Progress upto 31.01.2026
|
Sl. No. |
Description
|
Unit |
Total Scope as per CA |
Up to Date |
Up to Previous |
This Month |
Remarks |
|
(Length Kms) |
(Length Kms) |
(Length Kms) |
|||||
|
1 |
Site Clearance (C&G) |
Km |
2.930 |
2.930 |
2.930 |
|
|
|
2 |
Earthwork up to Subgrade Top-500mm |
Km |
2.930 |
2.930 |
2.930 |
|
|
|
3 |
CTSB-200mm (Cement Treated Sub Base) |
Km. |
2.930 |
2.930 |
2.930 |
|
|
|
4 |
AIL - 150 mm (Aggregate Inter layer) |
Km |
2.930 |
2.930 |
2.930 |
|
|
|
5 |
BC - 40 mm (Bituminous Concrete) |
Km |
2.930 |
2.930 |
2.930 |
|
|
Slip Road Progress upto 31.01.2026
|
Sl. No. |
Description
|
Unit |
Total Scope as per CA |
Up to Date |
Up to Previous |
This Month |
Remarks |
|
(Length Kms) |
(Length Kms) |
(Length Kms) |
|||||
|
1 |
Site Clearance (C&G) |
Km |
0.650 |
0.650 |
0.650 |
|
|
|
2 |
Earthwork up to Subgrade Top-500mm |
Km |
0.650 |
0.650 |
0.650 |
|
|
|
3 |
GSB - 200 mm (Granular Subbase) |
Km |
0.650 |
0.650 |
0.650 |
|
|
|
4 |
DLC-150mm (Dry Lean Concrete) |
Km |
0.650 |
0.650 |
0.650 |
|
|
|
5 |
PQC-280mm (Pavement Quality Concrete) |
Km |
0.650 |
0.650 |
0.650 |
|
|
|
Proposed treatment |
Unit |
Type |
Total scope in Sch-B |
Status
|
Achieved progress |
Remarks |
|
||
|
Status as on 31.01.2026 |
|
||||||||
|
Up to |
Up to previous |
This month |
|
||||||
|
Date |
|
||||||||
|
New Construction |
No. |
Box Culverts |
48 |
Completed |
48 |
48 |
0 |
Completed |
|
|
COS |
No. |
Box Culverts |
18 |
Completed |
18 |
18 |
0 |
Completed |
|
|
New Construction |
No. |
Minor Bridges |
6 |
Completed |
6 |
6 |
0 |
Completed |
|
|
New Construction |
No |
Major Bridge |
1 |
Completed |
1 |
1 |
0 |
Completed |
|
|
New Construction |
No |
VUP |
3 |
Completed |
3 |
3 |
0 |
Completed |
|
|
COS |
No |
VUP |
1 |
Completed |
1 |
1 |
0 |
Completed |
|
|
New Construction |
No |
LVUP |
12 |
Completed |
12 |
12 |
0 |
Completed |
|
|
New Construction |
No |
Elevated Structure |
7 |
Completed |
7 |
7 |
0 |
Completed |
|
|
COS |
No |
Elevated Structure |
1 |
Completed |
1 |
1 |
0 |
Completed |
|
|
New Construction |
No |
Inter Change |
1 |
Completed |
1 |
1 |
0 |
Completed |
|